What is involved in replacing/upgrading my switchboard?
Replacing or upgrading a switchboard requires a new switchboard, circuit breakers, safety switches, wiring and possibly new earth stake:
This is the process:
Harle's Electrical Home Page
This is the process:
- Remove old switchboard including marking cables (30-50 minutes)
- Wire new switchboard (3-4 hours)
- Install meters ready for Ergon to connect (1-2 hours - if using old meters)
- Testing (depending on test results could take up to 6 hours of rectifying problems